Integrate Construction Partners (Integrate) served as the general contractor on a recently completed $5.2 million renovation to the City of Kirkwood, Missouri’s community ice rink. Partnered with the owner’s representative, Navigate Building Solutions and Chiodini Architects, Integrate developed and completed a construction plan that prioritized schedule and efficiency to complete the project within the five-month schedule.
Located in the Kirkwood Community Center, the municipal ice rink was built in 1999 and generates a significant amount of revenue for the city’s parks and recreation department through its youth hockey and skating programs. The rink’s renovations were the final phase of an $11 million, three-phase project to upgrade the entire community center.
The ice rink renovations, which focused on modernizing key building systems and improving the performance and experience of the rink for athletes, families, and spectators, included replacement of the rink’s aging R-22 refrigeration system with a modern ammonia-based one due to the ozone-depleting properties of the older system’s freon refrigerant.
The renovation also included installation of new underground drain tile and concrete ice slab with 12 miles of refrigeration piping, new perimeter dasher boards and protective glass, upgraded heating and dehumidification systems, and LED lighting improvements, plus painting the overhead structure.
The rink’s final day of operation before the renovation was on February 26, 2026, with construction beginning immediately after the ice had thawed. The rink was scheduled to reopen on August 1, leaving less than five months to complete the project.
“Maintaining the project schedule was the city’s highest priority,” said Scott Zola, president of Integrate.
Demolition presented a logistical challenge on the project as an existing 8-foot-wide overhead door could not accommodate the standard dump trucks required for removal of the concrete rink slab and demolition debris. Without an alternative access point, the material removal would have required additional labor, negatively impacting the project schedule.
Looking for quick answers on air conditioning, heating and refrigeration topics?
Try Ask ACHR NEWS, our new smart AI search tool.
Ask ACHR NEWS
To overcome the site’s access limitations, the demolition subcontractor created a temporary opening through the north foundation wall that allowed dump trucks direct access into the facility. This solution streamlined demolition operations, reduced manual material handling, and helped maintain the accelerated construction schedule.
“Through strategic planning, coordination, and disciplined execution, the construction team modernized the rink’s critical infrastructure and delivered the project on schedule, providing the community with an upgraded facility built for long-term performance,” said Zola.
Because the project participated in Integrate’s community impact initiative, Integrate and several partners were able to make a $6,350 donation to the Kirkwood Parks Foundation at the project’s completion.
Whether you require installation, repair, or maintenance, our technicians will assist you with top-quality service at any time of the day or night. Take comfort in knowing your indoor air quality is the best it can be with MOE heating & cooling services Ontario's solution for heating, air conditioning, and ventilation that’s cooler than the rest.
Contact us to schedule a visit. Our qualified team of technicians, are always ready to help you and guide you for heating and cooling issues. Weather you want to replace an old furnace or install a brand new air conditioner, we are here to help you. Our main office is at Kitchener but we can service most of Ontario's cities